Technical Note
Function and Design
of the PHTS Hydrostatic Pressure Tester
as supplied to NB
Power, Bruce A Restart & OPG Darlington Unit 2
Purpose: To
test a Primary Heat Transport System (PHTS) that has been upgraded or modified
such that a hydrostatic pressure test is required by the Canada Nuclear Safety
Commission (CNSC) before the PHTS can resume operation.
The PHTS Pressure Test Requirement:
CNSC provides
the Operator (OPG/Bruce/NB Power) with a PHTS test pressure value that must be
maintained for 10 minutes. Typically the test pressure is 10% higher than the
operating PHTS design pressure. The actual PHTS pressure reading is observed on
several, 4 or more, pressure gauges located in the Main Control Room.
Technel Engineering Inc. Design: TEI has
designed and built three different, portable, temporary cart systems, sometimes
called Test Skids, each with different operator provided design requirement:
Basic Cart Design: The cart is designed to provide the required CNSC test pressure for 10
minutes at an unknown PHTS leak rate. The leaks emanate from new or
re-conditioned valves and possibly flanges. Although the leak from each valve
maybe in drops of D2O per minute, the quantity of valves and flanges results in
a leak rate of lpm.
The TEI design, see the attached OPG
schematic, uses a positive displacement pump **, a motor frequency (speed )
controller, a back pressure regulator, a high accuracy ( +/- 0.1% of reading)
digital pressure display, a flow display in lpm along with various valves,
safety pressure regulators and an analog pressure and temperature gauge. The
cart also has a surge tank ( ~100 litre capacity) that feeds the pump. The
surge tank level is maintained at a 50% - 75% level by a control tech operating
a manual make-up valve on the cart. The make-up water (D2O) is from an external
Operator source.
The actual operation is an iterative
process by which the cart control tech adjusts the pump flow rate (speed
controller) and the maximum pressure (back pressure regulator) till the cart
output matches the unknown PHTS leak rate and the required CNSC test pressure.
The operator control actions are based on
the actual pressure gauge readings in the control room. Based on those readings,
the control tech will increase/decrease motor speed (flow) and/or
increase/decrease the back pressure regulator.
Critical to a successful test is that after
every cart adjustment, motor speed and/or back pressure, significant time is
necessary to wait for the PHTS to react then settle to the latest adjustment.
This can take 20+ minutes for the last cart settings (flow rate and/or
pressure) to show up on the control room gauges. This is a must as the PHTS has
a long time lag due to the PHTS volume (300,000 litres +).
Based on the control room gauge readings,
the cart control tech will adjust up or down the flow and/or back pressure
until the leak rate is determined and the required test pressure is met.
** In Korea, a centrifugal pump is used.
Because of its design, this type of pump is more difficult to precisely adjust
the output pressure. The positive displacement pump speed can be adjusted in
0.1 Hz increments, resulting in small increments of flow and the resulting
increments in PHTS pressure.
A positive displacement pump provides flow
regardless of the system pressure that it is pumping into. As an example, it
will pump 10 lpm regardless of whether it is into a 20 kPa or a 20 MPa pressure
vessel.
William
Ormerod – May 2019
This
document contains information which is proprietary to and is the property of
Technel Engineering Inc. and may not be used, reproduced or disclosed in any
manner without express permission in writing from Technel Engineering Inc.